An Example Of How The Public Purse Is Protected In Other Jurisdictions That Ghana Ought To Learn From?

An interesting story in today's edition of 'The San Francisco Examiner', illustrates perfectly, how the Ghanaian nation-state ought to deal with contractors who produce either shoddy work, or deliberately execute government projects with wrong design specifications to enable them pay kickbacks to corrupt public officials, when they win bids for public procurement contracts.

We have culled the said story, today,  to serve as inspiration for President Akufo-Addo's government, and to inspire members of the relevant parliamentary committees that oversee public procurement contracts, so that they can see how the public purse is protected in other jurisdictions in the execution of public procurement contracts, and, if need be, recommend that news laws  are  passed  under certificates of urgency, to enable the same actions to be taken in Ghana in similar circumstances, going forward into the future.

The said 'San Francisco Examiner' story was written by Joe Fitzgerald Rodriguez, and is entitled: "City says Central Subway contractor laid down 3.2 miles of the wrong kind of track, prompting new delay".

Please read on:  

"The San Francisco Examiner       

Thursday May 10, 2018

Transit
City says Central Subway contractor laid down 3.2 miles of the wrong kind of track, prompting new delay

A contractor on the Central Subway project has laid down several miles of the wrong kind of track, according to San Francisco Municipal Transportation Agency. (Courtesy SFMTA)
By Joe Fitzgerald Rodriguez on May 10, 2018 1:00 am

Construction contractors on the $1.6 billion Central Subway project laid down 3.2 miles of the wrong kind of steel track, The City is alleging in a letter obtained by the San Francisco Examiner.

In the April 18 letter, The City ordered contractor Tutor Perini to pull out that track and lay higher-strength steel down in its place.

San Francisco Municipal Transportation Agency staff wrote to Tutor Perini alleging the contractor laid down 17,000 linear feet of “standard strength” steel, allegedly violating a contract with The City calling for “high strength” steel. The SFMTA said the higher-strength steel was selected to last longer before maintenance is required.

“This is not a safety issue,” SFMTA spokesperson Paul Rose wrote in a statement. But it may lead to another Central Subway delay.

Years ago, planners imagined Muni trains would roll through the Central Subway just after Christmas this year, on Dec. 26, 2018. But construction delays have seen that launch date slip to the end of next year. At an April 3 press event held 120 feet underground at Stockton Street, inside the future Central Subway Chinatown station, SFMTA Director of Transportation Ed Reiskin told reporters, “We’re holding with December 2019” for launch.

However, the allegedly incorrect track could lead to at least a month of delays, according to the agency, though the SFMTA is still negotiating its next steps with Tutor Perini. That lower-strength steel was laid from the opening of the tunnel at Fourth and King streets, where the Central Subway starts, to just past Market and Stockton streets, according to the SFMTA.

When Supervisor Jane Kim was told of the allegations, she exclaimed “No!”

“I want answers,” she said, “I think it certainly raises a lot of questions about the quality of our contract work.”

Supervisor Aaron Peskin has called for a hearing into Central Subway delays, which Kim supports. The subway runs through neighborhoods that both supervisors represent.

The letter written by SFMTA Program Manager of Project Delivery Eric Stassevitch to Tutor Perini Central Subway Program Manager Pat Jennings alleges that Tutor Perini and subcontractor Con-Quest Contractors “have been installing steel rails that are not in compliance with [contract] specifications.” Those specifications call for “high-strength, control cooled or vacuum treated carbon steel tee rail” meeting specific requirements.

“The SFMTA rejects the non-confirming standard strength rails,” Stassevitch wrote. He added, the “Contractor shall without delay remove [the Non-Conforming steel rail Work] from the Site and replace it promptly with Work and Materials that conform to the Contract Documents.”

Stassevitch also wrote that Tutor Perini must pay “all claims, costs, losses and damages.”

Gerald Cauthen, a retired supervisor engineer who helped build Green and Woods Muni rail yards and worked with Muni when the agency first launched the metro subway in 1980, told the Examiner the mess-up may have to be paid for by Tutor Perini. However, it is likely they may try to file claims against The City to recoup their costs.

“If The City has the proof on this one, I don’t see how Tutor can do anything but comply with it,” Cauthen said. The City might also use the alleged mistake to negotiate away other claims against the agency, he said.

“They’ve got ’em by the … you know,” Cauthen said.

Cauthen said the higher-strength rail may add “years” to the life of the track before replacement is needed.

“Trains run over the steel and it causes vacuum pockets,” he said. “Those pockets gradually get bigger and you can feel it if you ride that train.”

The SFMTA said it is unknown how much this will cost Tutor Perini or The City. Though the letter states Tutor Perini must “promptly” replace the steel, Rose said “we are working with the contractors” to “evaluate whether or not any of the current track can be used going forward.”

“These types of issues do come up on large projects like these,” Rose said in a statement.

Kim said nearby businesses experienced hardship from nearby construction, and even a month-longer delay could harm them. “They operate on such slight margins,” she said.

John Konstin, owner of John’s Grill at 63 Ellis St., said Central Subway construction caused foot traffic to his business to slow.

“There’s no accountability,” Konstin said. “So many people would have been fired if I were part of this job. It just keeps going on and on and on.”
Click here or scroll down to comment
Trending Articles

    Examiner Endorsements: June 5, 2018
    Farrell’s citywide internet plan could benefit transit, public health agencies
    San Francisco prepares for the bust after the boom
    Hunters Point Shipyard homeowners call for retesting of Parcel A
    San Francisco’s water conservation can flow to salmon

©2018 The San Francisco Examiner
Terms of Use | Privacy Policy."

End of culled content from the website of The San Francisco Examiner.

No comments: